House Remodeling Townhouse in Country Club

1971

Built

1,821 SF

Living Area

3 Bes / 2 Baths

House

Full remodeling of a Townhouse in Country Club

Residential Property built in 1971, Townhouse, with 1,821 SF of living area. 3bed/2bath.

Remodeling Goals:

It is an investment property, where the owners wanted a complete remodeling with the objective of having another property in Miami. The scope of the work is a total reconstruction of the townhouse, with an open concept modern design that would allow a pleasant stay in a property overlooking the golf course.

Before

DESIGN PROCESS

In the integration of the Open Concept Design process, the location of the kitchen was prioritized, whose position could be maintained but we needed to eliminate the dividing wall, allowing us to expand the kitchen and develop it towards the dining room, incorporating a central island. The bathrooms required a new design and distribution, wanting to eliminate the Jack and Jill bathroom and turn it into a larger and more comfortable bathroom for the handicap.
To start with the design, it was necessary to start with demolitions because we did not find records of the property plans and structural definitions were required. It was necessary to redo all the electricity, integrating the lighting with high hats and pendants in addition to all the underground plumbing because the existing one was cast iron, including the modification of the bathtub for a shower and the incorporation of new modern and functional cabinets in the bathrooms and the kitchen.

And immediately we discovered that the trusses were longitudinal and leaned on the kitchen partition, requiring a good structural solution to obtain the desired open concept design.

While the WGConstruction team of Architects and Engineers worked on the remodeling plans, we began to process with the City, the re-roofing permit that would allow us to start the work and prevent that future rains from allowing us to work inside

When the flat roof was finished and the inspections passed, we began to repair the damaged trusses.

Immediately after we began to place the tile re-roofing system.

In parallel to the re-roofing works, the WGConstruction Project team facilitated the As-built Plan (existing floor plan) and made us the proposal of the new floor plan for the approval of the Owners.

Once the floor plan was approved, the 3D renderings were proposed as part of the Design, to start working on the set of Architecture, Structure, Mechanics, Electricity and Plumbing plans that would allow us to process the corresponding Permits with the City.

The selection of the appliances by the Owners was essential for the shop drawing of the kitchen cabinets and to be able to start the manufacture of the custom kitchen cabinets.

The structural solution had been very important to complement the proposed and approved design. Due to the minimum height of the ceiling 96”, the reinforcing steel beams should not be placed below the trusses, that is, they should be placed between the logs

After obtaining all the corresponding permits, the structural reinforcement works began.

cc 81 cc 80 cc 79 cc 78 cc 77 cc 76 cc 75Toggle Content goes here

cc 82 cc 86 cc 85 cc 84 cc 83Toggle Content goes here

cc 87 cc 91 cc 90 cc 89 cc 88Toggle Content goes here

Within the proposal of the WGConstruction Project team was to eliminate the unevenness within the property, which was approved by the owners, and we filled the existing 5-6” difference with concrete.

Once the corresponding inspections were approved, we continue with the insulation, partitions, sheetrock, finish and primer paint works.

Floor installations begin, with tile selection by Owners and shipment.

After the tile installation was finished, the carpentry work began with the cabinets.

Enjoying the spectacular view of a Miami sunset and the perfect grass of the golf court are added values of this property that the Owners wanted to rescue.